LOTTE ECO SMART CITY
8 Years in the Making, 10 Days That Changed Everything

The story of Thu Thiem's most anticipated "diamond" project — and the pivotal ten days in August–October 2025 that nearly ended it all.

A Rocky Road (2017–2025)

2017

A Grand Beginning

Lotte Properties HCMC signs an investment agreement for an 11-tower mixed-use complex on 7.45 hectares at the core of Thu Thiem's financial district. Total committed capital: VND 20,100 billion.

2022

Groundbreaking — Then Nothing

Planning approval secured, groundbreaking ceremony held — but construction stalls at site clearance. Root cause: Ho Chi Minh City's land valuation process drags on for years with no resolution in sight.

June 2025

The Late-Payment Penalty Shock

Final land price set at VND 16,190 billion for the full 7.45 ha. But the Tax Authority then applies a 5.4% per annum late-payment penalty covering August 2022 to August 2025 — despite the delay being caused entirely by the government's own valuation backlog.
→ An additional ~VND 2,600 billion in penalties.

20 August 2025

The Breaking Point

Lotte formally submits a request to terminate the agreement and return the land to Ho Chi Minh City.

10 DAYS THAT CHANGED EVERYTHING

20 Aug → 03 Oct 2025

Market Reaction

Within days of Lotte's withdrawal news, the Sunshine–DIA consortium submitted a formal proposal to take over the project.

City's Move

HCMC had no intention of losing this "diamond" site. The Chairman of the People's Committee held direct talks with Lotte's senior leadership.

03 October 2025 — Lotte's 3 Conditions to Stay

  • Permission to restructure the equity ratio between subsidiary entities within the consortium.
  • Ability to bring in outside investors (up to 35% of total project capital).
  • Full waiver of the 5.4%/year late-payment penalty (~VND 2,600 billion).
HCMC accepted all three conditions. Lotte agreed to stay.

Where Things Stand (Early 2026)

50 Floors
Iconic tower reveal — H2/2026
>$2B
Total investment committed
2028–29
Projected handover
Zone 2A
Thu Thiem financial core

Active construction site: Infrastructure work and pile foundations are underway.
Design: CallisonRTKL & NBBJ  |  Main contractor: Lotte E&C

Our Take — Achieve Realty VN

What Holds Up

Lotte has paid the full VND 16,190 billion in cash — not a paper commitment. A 7.45-ha plot at the heart of Zone 2A is a one-of-a-kind asset. Crucially, when things got difficult in August 2025, Lotte negotiated — they didn't walk. That signals real intent.

What to Watch

The project is still at the foundation stage. From piles in the ground to key handover is a 3–5 year journey with real variables. This is not a play for those looking to flip or generate rental income in the near term.

WHO IS THIS PROJECT FOR?

Good fit if you:

  • • Are building long-term wealth and don't need immediate cash flow.
  • • Want a position in Thu Thiem's financial core from day one.
  • • Can accept timeline risk in exchange for an irreplaceable location.

Not the right fit if you:

  • • Need rental income within the next 1–2 years.
  • • Are looking to move in immediately or trade short-term.
  • • Prefer projects with fewer moving parts and a clearer timeline.

* Looking for a ready-to-rent alternative in Thu Thiem? Consider Metropole Thu Thiem or Zeit River Thu Thiem.

ACHIEVE REALTY VN

10th Floor, Miss Ao Dai Building
21 Nguyen Trung Ngan, Ben Nghe Ward, District 1, HCMC

View All Thu Thiem Projects →

+84 86 888 2539  |  +84 96 669 2202

sales@achievereal.com

Data compiled May 2026. Information is subject to change — please verify before making any investment decision.